Update on the Millennium Highway to Cul de Sac Roundabout Project.
By Ministry Of infrastructure
C. O. Williams has recently focused on road pavement works between the OKEU and Cul De Sac roundabouts, including junction improvements at the two junctions near the Sol Gas Station along the Millennium Highway. Progress at the Cul De Sac roundabout has been consistent, with the recent completion of the asphalt trial for arm 4, leading to the Millennium Highway. Ongoing works include the construction of the sidewalk along Arm 2 and preparation for the construction of the splitter islands on Arms 1 and 2. A significant upcoming task is the construction of Arm 3 at the Cul De Sac roundabout, planned to start in May. During this construction phase, traffic will be diverted through Arm 4 to connect the roundabout to the JICA bridge.